Level II scour analysis for Bridge 63 (CHESTH00090063) on Town Highway 9, crossing the Williams River, Chester, Vermont

Abstract

This report provides the results of a detailed Level II analysis of scour potential at structure CHESTH00090063 on Town Highway 9 crossing the Williams River, Chester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in eastern Vermont. The 24.0-mi 2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is grass with trees and brush along the immediate banks. In the study area, the the Williams River has an incised, sinuous channel with a slope of approximately 0.005 ft/ft, an average channel top width of 64 ft and an average bank height of 6 ft. The channel bed material ranges from gravel to boulder with a median grain size (D 50 ) of 57.7 mm (0.189 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 18, 1996, indicated that the reach was stable. The Town Highway 9 crossing of the Williams River is a 45-ft-long, two-lane bridge consisting of one 35-foot steel-beam span with a timber deck (Vermont Agency of Transportation, written communication, April 6, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 5 degrees to the opening while the opening-skew-to-roadway is 0 degrees. A scour hole 1.8 ft deeper than the mean thalweg depth was observed along the left abutment during the Level I assessment. The scour hole undermines the left abutment and extends from 50 ft upstream of the upstream bridge face to 50 ft downstream of the downstream bridge face. The scour protection measures at the site included type-3 stone fill (less than 48 inches diameter) under the bridge along the entire base length of the right abutment and along the right bank from 50 to 88 ft upstream. Type-2 (less than 36 inches diameter) stone fill scour protection was observed along the downstream left bank from 18 ft to 115 ft, along the downstream right bank from 8 ft to 25 ft and along the upstream left bank from 50 to 75 ft. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was computed to be 0.0 ft. Abutment scour ranged from 10.1 ft to 11.0 ft along the left abutment and from 14.1 ft to 15.1 ft along the right abutment. The worst-case abutment scour for the left abutment occurred at the 500-year discharge while the worst-case abutment scour for the right abutment occurred at the 100- year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Explore related subjects

90° N90° S · 180° W ← longitude → 180° E
Source-reported bounding extent: 43.25° to 43.375° latitude; -72.625° to -72.5° longitude. This indicates report coverage, not an exact sampling location. View area on OpenStreetMap.

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Robert H. Flynn. 1997. Level II scour analysis for Bridge 63 (CHESTH00090063) on Town Highway 9, crossing the Williams River, Chester, Vermont. https://doi.org/10.3133/ofr97423

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related USGS reports

ECCOE Landsat quarterly calibration and validation report—Quarter 2, 2026

Executive Summary The U.S. Geological Survey Earth Resources Observation and Science Calibration and Validation (Cal/Val) Center of Excellence (ECCOE) focuses on improving the accuracy, precision, calibration, and product quality of remote-sensing data, leveraging years of multiscale optical system geometric and radiometric calibration and characterization experience. The ECCOE Landsat Cal/Val Team continually monitors the geometric and radiometric performance of active Landsat missions and makes calibration adjustments, as needed, to maintain data quality at the highest level. This report provides observed geometric and radiometric analysis results for Landsats 8 and 9 for quarter 2 (April–June), 2026. All data used to compile the Cal/Val analysis results presented in this report are freely available from the U.S. Geological Survey EarthExplorer website: https://earthexplorer.usgs.gov.

Open-File Report↗

ECCOE Landsat quarterly calibration and validation report—Quarter 1, 2026

Executive Summary The U.S. Geological Survey Earth Resources Observation and Science Calibration and Validation (Cal/Val) Center of Excellence (ECCOE) focuses on improving the accuracy, precision, calibration, and product quality of remote-sensing data, leveraging years of multiscale optical system geometric and radiometric calibration and characterization experience. The ECCOE Landsat Cal/Val Team continually monitors the geometric and radiometric performance of active Landsat missions and makes calibration adjustments, as needed, to maintain data quality at the highest level. This report provides observed geometric and radiometric analysis results for Landsats 8 and 9 for quarter 1 (January–March) of 2026. All data used to compile the Cal/Val analysis results presented in this report are freely available from the U.S. Geological Survey EarthExplorer website: https://earthexplorer.usgs.gov . One specific activity that the ECCOE Landsat Cal/Val Team closely monitored was a Landsat 8 Thermal Infrared Sensor encoder alerts anomaly. On March 18, 2026, the Thermal Infrared Sensor instrument’s mechanism control electronics board reset, driving several parameters to default power-on values. Subsequent telemetry and analysis determined that no persistent hardware misconfiguration was present and no radiometric or geometric degradation was observed.

Open-File Report↗

Floods of June 20–July 6, 2024, in the Big Sioux River, Rock River, Little Sioux River, Ocheyedan River, and Floyd River Basins, northwestern Iowa

Major flooding occurred on June 20–July 6, 2024, in northwestern Iowa affecting the Big Sioux, Rock, Little Sioux, Ocheyedan, and Floyd River Basins. Heavy rain fell in northwestern Iowa, southwestern Minnesota, and southeastern South Dakota on June 20–22, 2024. Parts of northwestern Iowa recorded 2–6 inches of rainfall and localized amounts exceeding 12 inches. A maximum peak-of-record streamflow of 175,000 cubic feet per second at the U.S. Geological Survey streamgage Big Sioux River at Akron, Iowa (06485500), was recorded on June 22, 2024, and had an annual exceedance probability range of 0.2–0.49 percent. High-water marks were measured at four locations along the Big Sioux River between U.S. Interstate 29 at Sioux City, Iowa, upstream to Iowa Highway 10 north of Hawarden, Iowa, a distance of 75.7 river miles. A maximum peak-of-record streamflow of 157,000 cubic feet per second at the U.S. Geological Survey streamgage Rock River near Rock Valley, Iowa (06483500), was recorded on June 22, 2024, and had an annual exceedance probability of less than 0.2 percent. High-water marks were measured at eight locations along the Rock River between County Road B30 east of Hudson, South Dakota, upstream to Iowa Highway 9 at Rock Rapids, Iowa, a distance of 39.3 river miles. A maximum peak-of-record streamflow of 63,000 cubic feet per second at the U.S. Geological Survey streamgage Little Sioux River at Correctionville, Iowa (06606600), was recorded on June 24, 2024, and had an annual exceedance probability range of 0.2–0.49 percent. High-water marks were measured at 11 locations along the Little Sioux River between Iowa Highway 31 west of Correctionville, Iowa, upstream to U.S. Highway 18 north of Spencer, Iowa, a distance of 134.8 river miles. A maximum streamflow of 24,500 cubic feet per second at the U.S. Geological Survey streamgage Ocheyedan River near Spencer, Iowa (06605000), was recorded on June 22, 2024, and had an annual exceedance probability range of 0.2–0.49 percent. High-water marks were measured at three locations along the Ocheyedan River between County Road M38 west of Spencer, Iowa, upstream to U.S. Highway 18 west of Everly, Iowa, a distance of 12.8 river miles. A maximum streamflow of 41,000 cubic feet per second at the U.S. Geological Survey streamgage Floyd River at Alton, Iowa (06600100), was recorded on June 22, 2024, and had an annual exceedance probability range of 1–1.99 percent. High-water marks were measured at six locations along the Floyd River between Iowa Highway 3 at Le Mars, Iowa, upstream to Iowa Highway 10 at Alton, Iowa, a distance of 27.5 river miles. The high-water marks were used to develop flood profiles for the Big Sioux, Rock, Little Sioux, Ocheyedan, and Floyd Rivers.

Iowa, Minnesota, South Dakota↗